Demand management to defer 330 kV cable construction investment


Friday, 06 July, 2018

Demand management to defer 330 kV cable construction investment

New South Wales transmission operator TransGrid has opened a tender process to procure at least 40 MW of demand management solutions in Sydney’s CBD.

The process could defer more than $236 million of network investment, said TransGrid.

The network’s Powering Sydney’s Future (PSF) project is designed to reinforce the power supply to the inner city as cables supplying the area reach the end of their technical life and need to be retired.

As part of a proposal approved by the Australian Energy Regulated earlier this year, TransGrid will defer investment in a new 330 kV cable construction by procuring a variety of demand management solutions to reduce the risk of unserved energy to consumers in Sydney as existing infrastructure reaches the end of its serviceable life.

TransGrid’s tender process will run in two stages, allowing flexibility to procure more demand management should demand forecasts or cable conditions change.

The first stage is seeking 20 MW for this coming summer and 40 MW for the next three summers to 2021/22. This stage is currently open, closing on 31 July 2018.

The second stage is a ‘top-up’ round in addition to the first stage and will seek an additional 20–40 MW for summers 2020/21 and 2021/22. TransGrid anticipates this stage will commence in May 2020.

TransGrid’s Energy Services Manager, Rachele Williams, said the company had been encouraged by industry and stakeholder feedback in the lead-up to the tender process.

“We have seen a very strong response from non-network proponents in our early consultation, and there’s a lot of potential for deferring the commissioning of network infrastructure through the use of non-network solutions,” Williams said.

“In particular, we’re interested in non-network solutions to manage electricity demand to reduce risk in inner Sydney during summer heatwaves.

“We’ve seen a range of options from renewable generation, load curtailment, demand response and battery storage solutions.

“As far as we are aware, this is one of the largest capital expenditure deferrals by non-network solutions in Australia to date.”

Prospective tenderers can find more information at https://www.tenderlink.com/transgrid/.

Related News

100 years of SA's classic power pole

2024 marks the 100th anniversary of the distinctive Stobie pole — a steel-beamed power pole...

SA Power Networks to vastly expand use of drones

The utility has been working with Carbonix to advance the use of drones in aerial inspection work...

WA takes action following supercell thunderstorm damage

The WA Government is aiming to shore up its electricity supply following an extreme weather event...


  • All content Copyright © 2024 Westwick-Farrow Pty Ltd